Job Costing for Contractors: Budget vs. Actual by Cost Code, Explained
Most contractors know whether a job made money only after it is finished, when it is too late to fix. Job costing gives you that answer while the job is still running, line by line, so you can act on a problem in week two instead of discovering it at closeout.
Start with cost codes
A cost code is simply a label for a part of the job: demolition, rough framing, electrical rough-in, drywall, paint. Grouping every budget line and every cost under the same code is what makes comparison possible. Use a standard list so you can compare jobs with each other, and add your own codes for anything special to your trade.
The eight numbers that matter
- Original budget: what you planned to spend, usually from your estimate.
- Approved changes: approved change orders that add to or reduce the budget.
- Revised budget: original plus approved changes. This is your real target.
- Committed: money promised but not yet spent, such as purchase orders and subcontracts.
- Actual: money already spent: bills, expenses, approved labor hours, materials used.
- Remaining: revised budget minus actual.
- Forecast at completion: the most you are realistically going to spend, which is never less than what is already spent or committed.
- Variance: revised budget minus forecast. A negative number means you are heading over.
How to read it in two minutes a week
- Look at % used for each cost code. Anything above 90% deserves a look; above 100% is over budget.
- Compare % complete with % billed. If you have done 60% of the work but billed 30%, send an invoice.
- Watch projected margin over time. Saving a budget snapshot every week shows you profit fade before it becomes a loss.
Stop retyping numbers you already have
The biggest reason contractors give up on job costing is double entry. In WinkScope the Budget tab can be filled from the accepted estimate in one click, and these records count automatically:
- Approved change orders update the revised contract and budget.
- Approved time entries become labor cost (hours times rate).
- Vendor assignments and purchase orders become commitments.
- Approved vendor payments, bills, expenses and inventory marked as used become actual cost.
- Invoices and payments fill billed, collected and outstanding.
Share the right version
Your internal job cost report includes costs and margin. Your client should not see that. WinkScope's Download button offers an internal report and an owner report that leaves out internal costs, as Excel or a branded PDF.
FAQs
Do I need accounting knowledge to use job costing?
No. If you can read an estimate, you can read a budget by cost code.
Will it warn me before a line goes over?
Yes. Lines turn amber near their limit and red when over, and owners get notifications at the alert levels you choose (80, 90 and 100% by default).