Save a budget baseline

Short answer

Click Save baseline in Budget, or type a name in Reports > Budget baselines and click Save. Full steps below.

Where: Project > Financials > Budget

Plans: Enhanced project dashboard plans (Overview, Change Orders and Invoices & Payments are on all plans)

Steps

  1. Click Save baseline in Budget, or type a name in Reports > Budget baselines and click Save.
  2. A baseline freezes every budget line, total and margin at that moment.
  3. Open it with the eye icon, or compare any two (or one with Now) in Reports > Compare, then click Excel or PDF to download the comparison.

Rules and limits

Still stuck?

If a step does not match what you see on screen, stop there and open a ticket from Support > My Tickets with a screenshot of that step. The team will look at the account directly.

Last verified 2026-11-18.