Financials: Commitments, retainage, lien waivers

Short answer

Purchase orders and subcontracts with number (auto PO-001 / SC-001 if left blank), vendor, cost code, status (draft, sent, approved, closed, cancelled), amount, retainage %, issued date, and for subcontracts lien waiver received and insurance expiry. The table shows billed (bills linked to it), remaining and retainage held (billed x retainage %). Checks flag 'No lien waiver', 'Insurance expired' and 'Billed over amount'. Only orders that are not Draft or Cancelled count as committed.

Where: Project > Financials > Commitments

Plans: Enhanced project dashboard plans (Overview, Change Orders and Invoices & Payments are on all plans)

Add a purchase order or subcontract

  1. Open Financials > Commitments.
  2. Click Purchase order or Subcontract.
  3. Enter vendor, amount, cost code, status and retainage %; for subcontracts add insurance expiry and tick Lien waiver received when you have it.
  4. Click Save. Link bills to it from the bill form.

Still stuck?

If WinkScope does not behave the way this page describes, do not work around it. Open a ticket from Support > My Tickets with the page you were on and a screenshot, and the team will look at the account directly.

Last verified 2026-11-18.