Revised = original + approved changes. Remaining = revised - actual. Forecast = the larger of revised, committed and actual. Variance = revised - forecast (negative means heading over). % used = actual / revised.
Each column
Original: quantity x unit cost (or the typed amount when that is zero).
Changes: approved or invoiced change orders, using their before-tax subtotal; deductions are negative.
Committed: purchase orders and subcontracts that are not Draft or Cancelled, plus confirmed vendor assignments.
Actual: bills and expenses (net of tax when the amount includes tax), approved time entries (hours x rate), approved or paid vendor payments, older cost entries and inventory used.
Projected profit: revised contract - forecast at completion. Projected margin: that profit / revised contract.
Project-level figures
Revised contract = original estimate total + approved change order totals.
% complete by cost = actual / forecast at completion.
Over- or under-billed = billed - (% complete x revised contract).
Retainage held = bills linked to each commitment x that commitment's retainage %.
Still looks wrong?
Check Costs & Bills > Costs already recorded elsewhere in WinkScope to see each source. If a figure still does not match, open a ticket from Support > My Tickets with the project name and the number you expected.