How budget numbers are calculated

Short answer

Revised = original + approved changes. Remaining = revised - actual. Forecast = the larger of revised, committed and actual. Variance = revised - forecast (negative means heading over). % used = actual / revised.

Each column

Project-level figures

Still looks wrong?

Check Costs & Bills > Costs already recorded elsewhere in WinkScope to see each source. If a figure still does not match, open a ticket from Support > My Tickets with the project name and the number you expected.

Last verified 2026-11-18.