Open the project, go to Schedule > Gantt, click Add and choose Let WinkScope AI build it. Full steps below.
Where: Schedule > Gantt Chart tab, and inside a project: Projects > open project > Schedule > Gantt
Plans: Pro, Agency and Enterprise (or an active trial)
Steps
Open the project, go to Schedule > Gantt, click Add and choose Let WinkScope AI build it.
Optionally add notes (crew size, order of rooms), then click Build my plan. WinkScope AI reads the project's scope and line items and suggests phases, tasks, durations, milestones and checklists, linked in order.
Review the plan. Set a start date (an upcoming project start date is filled in for you) or leave it empty to start from today as a placeholder, then click Add to Gantt.
Please review the dates afterwards: drag bars or open a task to adjust anything.
Rules and limits
The Schedule page is included from Pro upward. Starter and Free plans see an upgrade prompt instead of the calendar.
WinkScope AI only plans work the scope implies; it does not add extra trades or prices, and its dates are suggestions the user should review.
The AI plan is added only after the user clicks Add to Gantt.
What this cannot do
Pull in dates from Google Calendar to build the plan.
Drag sub-task rows that live inside a task directly; open the parent task to edit them.
Still stuck?
If a step does not match what you see on screen, stop there and open a ticket from Support > My Tickets with a screenshot of that step. The team will look at the account directly.