Click a bar to open the task, then go to its Gantt options. Full steps below.
Where: Schedule > Gantt Chart tab, and inside a project: Projects > open project > Schedule > Gantt
Plans: Pro, Agency and Enterprise (or an active trial)
Steps
Click a bar to open the task, then go to its Gantt options.
Under Before, choose the tasks this one waits on; under After / Next up, choose the tasks that wait on this one. The arrows on the chart follow those links.
Pick the link type (finish to start, start to start, etc.) and optional gap days. Links that would make tasks wait on each other in a loop are refused.
Rules and limits
The Schedule page is included from Pro upward. Starter and Free plans see an upgrade prompt instead of the calendar.
WinkScope AI only plans work the scope implies; it does not add extra trades or prices, and its dates are suggestions the user should review.
The AI plan is added only after the user clicks Add to Gantt.
What this cannot do
Pull in dates from Google Calendar to build the plan.
Drag sub-task rows that live inside a task directly; open the parent task to edit them.
Still stuck?
If a step does not match what you see on screen, stop there and open a ticket from Support > My Tickets with a screenshot of that step. The team will look at the account directly.