Jobs and tasks are scheduled blocks of work. They can be all-day or given explicit start and end times, and can be attached to a project.
Where: Schedule > add button > New Job/Task, or a project's Schedule tab
Plans: All plans
Schedule a job or task at a specific time of day
Open Schedule and click the add button, then New Job/Task.
Fill in the title and dates.
Turn off the all-day option to reveal the Start Time and End Time fields, and set them.
Save. Changing the date later keeps the times you entered.
Add more tasks to a project that is already approved
Open the project from Projects, then the Schedule tab.
Add as many tasks and phases as needed — an approved project can hold any number of scheduled items.
Still stuck?
If WinkScope does not behave the way this page describes, do not work around it. Open a ticket from Support > My Tickets with the page you were on and a screenshot, and the team will look at the account directly.