Project pages: Change Orders, Work Orders, Photos, Documents, Invoices

Short answer

Each project tile opens its own page: Changes opens the project's Change Orders page (create and see all change orders), Work Orders opens the Work Orders page, Photos opens the Photos page, Documents opens Documents (uploaded files, estimates, invoices and change orders plus the Documents Studio), Financials and Logs & Notes open their pages. Invoices stay on the project dashboard under the To-Do list. To-Dos sort open items first by the nearest due date, then undated, with completed last; both cards scroll inside themselves.

Where: Project dashboard tiles

Plans: All plans

Find the change orders for a project

  1. Open the project.
  2. Click the Changes tile.
  3. Click Create change order or open an existing one.

Still stuck?

If WinkScope does not behave the way this page describes, do not work around it. Open a ticket from Support > My Tickets with the page you were on and a screenshot, and the team will look at the account directly.

Last verified 2026-11-26.